Proposal for Planning and Managing Elements of a public Project Academic Essay

 

Description/Overview

This report presents a proposal plan for a small public recreational park in the middle of the city. In the present era entertainment and recreational activities have gain an immense importance of the general public as well as of tourist. Today, people enjoy spending time in outdoor activities, where they could have quality for them and their children. In this regard, the plan of a recreational plan having recreational activities for both children and adults is proposed. Adults’ activities will include a golf court, 2 baseball fields (one for children and one for adults), 1 outdoor tennis field, toddlers playing area, rides area for children and teenagers, refreshment stall and a walking track. The rest of the park area will be left as an open area with benches, trees and lawns for people coming just for relaxation. The entrance to the park will be free; however, people will have to buy the entry pass for each playing area. Membership cards will also be offered for regular visitors.

Scope Statement

This project will assist in enhancing the quality of life of people living in the region through leisure, outdoor recreational activities and providing natural and relaxing environment. This project will provide economical, social and environmental benefits to the government. Government will get funds from the profits earned through passes and the taxes paid on every sale. While, the intangible benefits are providing a peaceful place to its citizens. Another benefit for both government and people is to have more greenery and beauty around that could be a source of freshness for everyone.

The project scope statement is presented in the following checklist form:

Project Justification To convert an unused, abundant land into a recreational area as a step toward redevelopment of the community and opening economical, social and tourism opportunities in the region.
Project Objectives ·         To meet the recreational needs of the community as recreation improves the quality of life in which we live, play, visit and work.

·         To contribute in increasing plantation while creatively using the natural environment.

·         Improving public health.

·         To promote tourism.

Milestones ·         Proposal Approved

·         Site Finalization

·         Site Construction Complete

·         Completion Of Recreational Activities Area

·         Completion Of Open Area

·         Park Ready For Opening

Resource Requirements ·         Construction team

·         Building engineers

·         Management team

·         Architects

·         Plantation partners

·         Office supplies

·         Cleaning and Maintenance team

·         Play areas Equipments and sports Goods

·         Retail pads and tickets

Constraints ·         Need to search for investors as the resources are limited.

·         Needs the proposal to be accepted soon

Assumptions ·         The land is suitable for plantation

·         The space is enough for all activities

·         The location is easily approachable by the citizens; has direct roads.

·         The land is free from any kind of harmful toxins and water drainage.

 

Cost and Benefit Analysis

The cost and benefit analysis of this project is highly depended on the number of visitors, its operations and management effectiveness and government support. The financial benefits expected from this project are the profits earned from the sales of passes, membership cards, rents from refreshment stall owners and car parking slots. These profits will be calculated after deducting the expenses incurred for all the operations and maintenance of the park. The investors will also be given the share of their profits. The social benefits for the community will be having a place where they could meet each other, could have quality time with family and could engage in physical activities. Hence, overall the social benefit is the health care of the community. Another intangible benefit is the increased number of natural beauty and freshness. These benefits are mostly considered as long term benefits. Once the park is able to attract people, the number of visitors will increase gradually.

On the other hand, the major cost of the project is incurred in the beginning, during the construction of the park. It’s more of a onetime huge investment. The basic cost of the park is its construction and installation of recreational activities equipments.

The estimated cost for the project is $ 515,500.00 which will be collected from investors and sponsors. However, efficient management will be carried to ensure minimum cost and to maintain the budget of the plan.

 

 

 

 

For Builder

Respected Authorities

To whom it may concern

This construction contract is made by and between the project manager of the new recreational Park project and the construction company with the desire to obtain and provide the construction services respectively.

Therefore, in consideration of the mutual promises set forth below, the parties agrees as follows:

  1. Description of the services: the builder company will provide the services of :
    1. Segmentation of the land
    2. Construction of the fields
    3. Construction of the building
    4. Construction of car parking area
    5. Installation of electric system and IT requirements

 

  1. Scope of Work: the contracting construction company will provide all the services, material and labor required for the construction of the whole recreational park. This will include all the construction material, tools, machinery, equipment, playing area accessories and furniture, labor requirements, and site security.

 

  1. Payment: Payment shall be made to the tender winning company. The hiring company agrees to pay $200,000.00 for the construction of the whole project with the payment to be made in 3 installments. One installment will be paid before the beginning of the project; the second will be paid in midway and third will be paid after the completion of the project.
  2. Time: the project is planned to be completed within 280 days so the contracting company shall complete the task on or before the defined dates.

 

The construction company is expected to agree on all the above mentioned terms and conditions. The construction team members are also expected to ensure 100% co-operation with external parties and supporting project management teams.

 

Regards,

Project Manager

Signature of Contractor

 

Signature of Contracted

 

 

 

 

 

 

 

 

 

For Design

Respected Authorities

To whom it may concern

This Designing contract is made by and between the project manager of the new recreational Park project and the designing company with the desire to obtain and provide the infrastructure and building design services respectively.

Therefore, in consideration of the mutual promises set forth below, the parties agrees as follows:

  1. Description of the services: the designing company will provide the services of :
    1. Site consideration; detail area plan
    2. Streetscape and building design (front and secondary elevations)
    3. Giveaways and crossways design
    4. Ancillary work (fencing, benches placements, waiting area design)
    5. Landscaping
    6. Painting and Furnishing of the play areas

 

  1. Scope of Work: the designing company will perform all design, design management, construction management services, and will provide all supplies, equipment, facilities, tools and labor, material necessary to complete the Work described in and reasonably inferable from the Contract Documents.

 

  1. Payment: the contract price will be equal to Design-Builder’s Fee plus the Cost of the Work, subject to any adjustments made in accordance with the General Conditions of Contract.

 

  1. Time: the project is planned to be completed within 280 days so the contracting company shall complete the task on or before the defined dates.

Design-Builder shall procure insurance in accordance with the General Conditions of Contract.

Regards,

Project Manager

Signature of Contractor

Signature of Contracted

The below table presents the Breakdown of the project in to all of its tasks and sub-tasks

Task Name Duration Start Finish
Construction of a recreational park 280 days Mon 4/18/16 Fri 5/12/17
developing project plan 49 days Mon 4/18/16 Thu 6/23/16
   Preparation of the project plan 18 days Mon 4/18/16 Wed 5/11/16
   Project plan approved 6 days Thu 5/12/16 Thu 5/19/16
   Searching for Investors 14 days Thu 5/12/16 Tue 5/31/16
   Funds Raised from investors 17 days Wed 6/1/16 Thu 6/23/16
Procurement 33 days Fri 5/20/16 Tue 7/5/16
   contracting work force 10 days Fri 5/20/16 Thu 6/2/16
   hiring construction team 8 days Fri 6/24/16 Tue 7/5/16
   Hiring landscape team 9 days Fri 6/3/16 Wed 6/15/16
   Hiring Management Team 11 days Fri 6/3/16 Fri 6/17/16
Resources Allocation 16 days Wed 7/6/16 Wed 7/27/16
   Supplying Resources to Contracting teams 16 days Wed 7/6/16 Wed 7/27/16
Site Acquisition 12 days Thu 7/28/16 Fri 8/12/16
   Approval of Site 6 days Thu 7/28/16 Thu 8/4/16
   Acquisition of Site 6 days Fri 8/5/16 Fri 8/12/16
Design Finalization 50 days Thu 7/28/16 Wed 10/5/16
   Preparing the Design Draft 29 days Thu 7/28/16 Tue 9/6/16
   Reviewing the Design 11 days Wed 9/7/16 Wed 9/21/16
   Design Approved 10 days Thu 9/22/16 Wed 10/5/16
Land Preparation 77 days Thu 10/6/16 Fri 1/20/17
   Land Clearance 39 days Thu 10/6/16 Tue 11/29/16
   Division of Land in segments 23 days Wed 11/30/16 Fri 12/30/16
   Excavating the foundations of fields and buildings 15 days Mon 1/2/17 Fri 1/20/17
Preparation of play area fields 85 days Mon 1/23/17 Fri 5/19/17
   building construction 32 days Mon 1/23/17 Tue 3/7/17
   installation of resources/equipments 22 days Wed 3/8/17 Thu 4/6/17
   Technical supplies and furnishing 17 days Fri 4/7/17 Mon 5/1/17
   completion of fields 14 days Tue 5/2/17 Fri 5/19/17
Landscaping 80 days Wed 11/30/16 Tue 3/21/17
   Installation of irrigation systems 38 days Wed 11/30/16 Fri 1/20/17
   Planting trees and plants 18 days Mon 1/23/17 Wed 2/15/17
   Gardening 24 days Thu 2/16/17 Tue 3/21/17
Final Detailing 11 days Mon 5/22/17 Mon 6/5/17
   Reviewing of task against Standards 11 days Mon 5/22/17 Mon 6/5/17
Park Ready for Operation 7 days Tue 6/6/17 Wed 6/14/17
   Park Inauguration 7 days Tue 6/6/17 Wed 6/14/17

 

Costing

The costing of the plan is presented in dollars

Task no Task Name cost
  Construction Of A Recreational Park  $     515,500.00
1 Developing Project Plan  $              500.00
2 Procurement  $        50,000.00
3 Resources Allocation  $        10,000.00
4 Site Acquisition  $     100,000.00
5 Design Finalization  $        20,000.00
6 Land Preparation  $        10,000.00
7 Preparation Of Play Area Fields  $     200,000.00
8 Landscaping  $     100,000.00
9 Final Detailing  $        10,000.00
10 Park Ready For Operation  $        15,000.00

 

 

 

 

 

 

 

 

 

 

 

 

 

The total estimated cost for the plan is $ 515,500.00. While keeping $65,000.00 as a profit margin for the company, the total cost for the plan is $580,500.00.

Please refer to the Project Management attached file.